The Hidden Cost of Customising a Replacement Package to Match the Old System
When an organisation buys a package to replace a home-grown or heavily modified system, a familiar pattern often follows. Users compare every screen with the old one and ask for changes until the new system behaves like the old. Each request seems reasonable. Together they can recreate the very problem the replacement was meant to solve: software that is hard to upgrade and understood by too few people.
Configuration, extension and customisation
It helps to separate three kinds of change, because they carry very different long-term costs.
| Type | What it is | Effect on upgrades |
|---|---|---|
| Configuration | Settings, workflows and fields the vendor supports | Usually carried forward automatically |
| Extension | Add-ons built through the vendor’s published extension points or interfaces | Usually survives, but needs testing |
| Customisation | Changes to the product’s own code or database structures | Often must be redone or retested at each upgrade |
Vendors generally recommend staying with configuration where possible, and many will not support problems in customised areas. Before signing, ask the vendor how each kind of change is treated in their upgrade and support terms.
A decision rule for each request
For every request to make the new system behave like the old, ask three questions in order:
- Can the process change instead? If the old way existed only because of the old system’s limits, adopting the package’s standard approach may be better.
- Can configuration achieve it? Many requests can be met with settings, report layouts or workflow options the vendor already provides.
- Is it a genuine differentiator? If the process is part of what makes the organisation distinctive or compliant, an extension or customisation may be justified. Record the reason and the expected upgrade cost.
The people side of saying no
Refusing a customisation can feel like ignoring users. The way to make it acceptable is to explain the trade-off openly and to involve users in redesigning the process. A small group trying the package’s standard approach for a fortnight, with support, often concludes it is fine or even better. Where it is not, their evidence makes a strong case for an exception.
Sponsors play a part too. If every customisation decision is escalated and approved to avoid conflict, the programme drifts. A clear principle agreed at the start, such as “standard unless there is a legal, contractual or competitive reason”, gives the project team something to point to.
Keeping a customisation register
Log every approved change beyond configuration, with its reason, owner and estimated upgrade effort. Review the list before each major vendor release. Over time you may find that the vendor has added a standard feature that lets you remove a customisation, which is one of the cheapest improvements available.